|
September 8, 2014
Hand
Delivered
Ms. Felice P. Congalton
Associate Director
Office of Disciplinary Counsel
Washington State Bar Association
1325 Fourth Avenue, Suite 600
Seattle, WA 98101
RE: ODC File
Nos. 14-01156; 14-01157; 14-01158; 14-01159
Grievants: Mark
and Carol DeCoursey
Respondents:
Robert M. Sulkin, Malaika M. Eaton, Ryan P. McBride, and Grant
Degginger
Dear Ms. Congalton:
Please consider this letter to the
reply to the Respondents' “preliminary written response.”
It is divided into two sections with separate page numbers:
Introduction and list of
undisputed violations, follows directly after this page.
Rebuttal of Respondents'
arguments, presenting quoted passages from the Response, with direct
rebuttals.
I. Introduction
In adjudicating this matter, the
Consul must not lose sight of the key question: Have these lawyers
violated the codes and standards required of practicing attorneys in Washington?
The Respondents have wandered (and
would lead this tribunal) into many other matters, but really the
questions are rather simple. This is not a trial of our characters,
despite the Respondents' efforts to make it such.
They attempt to justify their
mendacity by pointing out that Judge Ricard D. Eadie, who presided
over Lane Powell v. Mark & Carol DeCoursey, allowed them
to lie and incorporated their the lies into his rulings. But WSBA
has no jurisdiction over Judge Eadie. WSBA has jurisdiction over
attorneys. This is not a rehash of the trial, though some issues
overlap. This is not even a review of whether the judge should have
been recused -- that too is outside purview of this body. The
judge's recusal is interesting only on the issue of whether his
decisions may be consider prima facie correct. The Respondents seem
to argue from the position that whatever the judge ruled, this body
must also agree. However, the judge's qualification to preside over
this case is a question still before the courts. And this body works on a different standard of proof over a different set of laws
and rules. This body is not even confronted with the same set of
facts. Therefore, this body should not consider itself bound by the
decisions of the court.
Let us review the violations of the
RPC of which we have complained in our Grievance, and take an
accounting of which the Respondents dispute. In the process, we
construct a list of the violations to which the Respondents tacitly
admit culpability. The various violations will be listed in sequence
as they appear in the Grievance, which is roughly chronological.
All acts performed on behalf of Lane
Powell by the lawyers at McNaul Ebel were performed on behalf of
McBride and Degginger, who are full partners in Lane Powell. The
other Respondents have designated Malaika Eaton to represent and
answer for them in this matter. Therefore, let them stand or fall by
the response she has provided – or failed to provide.
Respondents also lie to WSBA about
myriad issues, offending against Title 8 of the Rules of Professional
Conduct. Will WSBA tolerate that?
Either WSBA will discipline those
who flagrantly and repeatedly violate the Rules of Professional
Conduct, or WSBA will tell the world that -- in the State of
Washington -- it is OK for lawyers to lie in court and commit other
flagrant violations of the Profession and their Oath to the Bar –
and OK, too, for Washington lawyers to lie to the WSBA Disciplinary
Counsel.
What the Respondents did, they did
boldly, without any fear they would be disciplined. And even now,
despite our documentation of their misdeeds before the Washington
State Bar, they still have no fear of discipline. It appears that
they fully expect WSBA will permit them to get away with lies they
told in court: Flagrant and repeated violations of RPC 3.3, “Candor
Towards the Tribunal,” and many others.
Note: This is a summary only. Full
details are in the text of the original Grievance and are not
repeated here. The words “Disputed” and “Not
disputed” refer to the Response and whether the Respondents
disputed the particular point in the Grievance. Page numbers, where
they appear, refer to the pages in the Grievance.
RPC 1.5: Whatever errors were
committed by our attorneys of record, they were junior associates in
the firm under the supervision of Degginger; therefore, any and all
errors were Degginger's errors. | P. 39. | Not
disputed. | |
RPC 1.7, 1.8, 1.9
(particularly 1.7(a)(2)): Degginger failed to disclose his
positional and political conflict of interest with our opponents in
the real estate profession, both before approving the retainer
agreement, and again before taking direct control of the case. | P.
40. | Disputed. | |
RPC 1.7, 1.8, 1.9
(particularly 1.7(a)(2)): As mayor of Bellevue, Degginger failed to
disclose his natural and positional alliance with the sister city of
Redmond when he approved the retainer agreement, then required us
dismiss Redmond as a defendant on his misapplication of the Public
Duty Doctrine. | P. 40. | Not disputed. | |
RPC
1.2 (RPC 1.0(e)): Degginger
did not disclose that he had exempted himself from the Lane Powell
conflicts disclosure prior
to engagement. | P.
42. | Not disputed. | |
RPC 1.2 (RPC 1.0(e)):
Degginger failed to have us consult independent counsel prior to
signing the retainer agreement to warn us of its pitfalls. | P.
43 | Not disputed. | |
RPC 1.2, 1.8: Degginger did
not tell us that the Lane Powell firm had been instrumental in
eviscerating the legislative intent of the Consumer Protect Act
(CPA) by padding its bills in the 1987 case Nordstrom v.
Tampourlos. As a
result of that case, the recovery of fees and costs under the CPA is
severely limited. | P.
45. | Not
disputed. | |
RPC 1.2 (RPC 1.0(e)):
Degginger did not disclose to us that any confidences given in the
attorney client relationship (and confidences he might allege) could
and would be used to blackmail us if fee dispute arose. | P.
45 | Not disputed. | |
RPC 1.7, 8.4:
Prior to
signing us to the retainer agreement, Degginger failed to disclose
the risks of associated with the lawyer's dual role as both legal
adviser and participant in the transaction. | P. 46. | Not
disputed. | |
RPC 1.8: Degginger admitted
to the Court that he had acquired a proprietary interest in the case
by arguing repeatedly that the Court had awarded fees to Lane
Powell. | P. 46. | Not disputed. | |
RPC 3.2: Degginger did not
tell us that, by policy, Lane Powell did not use the Court Rules
designed to expedite litigation, but took the long and expensive
route of answering every spurious motion from opponents. | P.
48. | Not disputed. | |
RPC 1.8: Degginger did not
tell us that he intended to churn the case until we ran out of
money, and then would continue the case on credit making us unable
to terminate the relationship. Thereby, Degginger would acquire a
proprietary interest in our case, enabling him to turn it to his
purposes, harvest the damages as legal fees, and mitigate the damage
to his political friends and supporters in the real estate industry.
| P. 48. | Not disputed. | |
RPC 8.4:
Though it had a duty to disclose all material facts and conflicts of
interest prior to engagement, Degginger concealed multiple material
facts in the signing of the retainer agreement. This was a
violation of multiple statutes and principles of law, in addition to
explicit clauses of the RPC. | P. 40-52. | Not
disputed. | |
RPC 1.7, 1.8, 1.9
(particularly 1.7(a)(2)): As the husband of a lawyer who had worked
in the Attorney General's office for 18 years, Degginger did not
tell us that his natural sympathies through his wife lay with the
political insiders we were opposing and had worked to expose.
| P. 52. | Not disputed. | |
RPC
1.2, 1.3: Degginger's team pressured us to settle
with the contractor and
his company on
a highly reduced scale, barely covering the legal fees incurred by
wrestling
with those
litigants
and negotiating a settlement, and not covering the damages.
Degginger
absorbed the lion's share in fees and created a continuing issue for
legal argument thereafter, consuming more fees. | P.
55. | Not
disputed. | |
RPC 1.2, 1.3: Degginger
preemptively set the goals for the case in favor of his political
friends and supporters in the real estate profession, and did not
operate us on our own goals for the litigation. | Not
disputed. | |
RPC 1.2, 1.3: Degginger's
team refused to move the court for summary judgment on the argument
that the defendants had admitted the key elements of the case under
CR 8(d). Such a motion could have reduced Lane Powell's final bill
by hundreds of thousands of dollars in fees. | P. 56. | Not
disputed. | |
RPC 1.2, 1.3: Degginger's
team pressured us to admit the opponents' experts into the house
after the close of discovery to further an alleged settlement.
| P. 56. | Not
disputed. | |
RPC 1.2, 1.3: Degginger's
team pressured us to sell the house in settlement to our opponents
to satisfy the legal fees, and leave ourselves without money and
without a home. | P. 56. | Not
disputed. | |
RPC
1.2, 1.3:
Degginger's
team persisted
and billed
us for the time spent on the RPC
1.2, 1.3 violations
listed above, despite our repeated insistence that Lane Powell
should cease all work in those directions. | P.
56. | Not
disputed. | |
RPC 1.2, 1.3: Degginger's
team urged us to settle for a catastrophic loss after the
expense of a trial and
before the jury verdict. | P.
58. | Not
disputed. | |
RPC
1.7,
1.8,
1.9:
Degginger
personally admitted that Lane Powell had an institutional conflict
of interest with our case; that our victory was “not good for
Lane Powell.” | P.
59. | Not
disputed. | |
RPC
1.2, 1.3:
Without
telling us, Degginger's team failed to move the court for the CPA
triple damages award, despite the jury verdict finding
the defendants in violation.
| P.
59. | Not
disputed. | |
RPC
1.2, 1.3:
Without
telling us, Degginger's team failed to tax Windermere for several
months of legal fees when computing its motion for fees under the
CPA. Once more, Degginger's political friends and supporters
benefited by Degginger's friendship. | P.
60. | Not
disputed. | |
RPC
1.8(h)(1): Degginger's team
insisted
on having
us sign an agreement that
prospectively
limited any
claims
of malpractice. | P.
61. | Disputed. | |
RPC
1.7, 1.8, 1.9: Degginger's team pressured us into signing a modified
fee agreement that it wrote without advising us to seek independent
legal advice. | P.
61. | Not disputed. | |
RPC 1.5, 1.8 Comment 3:
Degginger treated our case as a contingency case without our express
agreement, and while still charging hourly. | P. 61. | Not
disputed. | |
RPC
1.2, 1.3:
Without
telling us, Degginger's team failed to tax Windermere for the
$21,000 in (alleged) costs Lane Powell had advanced to us at
the fees motion hearing. That claim was almost lost as a result.
| Not disputed. | |
RPC
1.2, 1.3, 1.4:
Because the judgment was founded on the REPSA contract as well as
tort, the Judge Fox had originally ordered 12% post-judgment
interest. Without informing us, Degginger's team made a secret
agreement with our Windermere opponents to discount the post
judgment interest rate ordered by the judge (12%) to a rate far
below the lowest statutory rate (3.935%). Degginger's team
specified 3.49% in the judgment by request of the opponents'
attorney. | P. 62. | Not disputed. | |
RPC
1.1,
1.2,
1.3:
Degginger
personally
advised us contrary to fact and law by insisting
that the discounted post-judgment interest rate of 3.49% must
prevail, even after the legislature had retroactively raised the
rate to 5.25%. | P.
62. | Not disputed. | |
RPC
1.1,
1.2,
1.3: McBride failed to ask for a reconsideration after
the Court of Appeals reversed a court ruling that had not been
challenged or argued by the appellant, despite Lane Powell's
specific written contractual promise (Dec. 30, 2008 agreement):
“Lane Powell will also help you with regard to the same as
necessary to prevail in or retain the awards discussed.” | P. 63, 74.
| Disputed only on the issue of whether he should have done so.
Otherwise Not disputed. | |
RPC 8.4(c): McBride and
Degginger lied to us about the current practice of limiting the CPA
costs fees to those listed in RCW 4.84.110. The practice was not
established by statute, but by Lane Powell's own case, Nordstrom
v. Tampourlos, 107 Wn.2d 735, 733 P.2d 208 (1987). | P. 71. | Not
disputed. | |
RPC
1.1,
1.2,
1.3: McBride
failed to move the Court of Appeals for the nine hours of fees
incurred in composing his affidavit of fees. | P.
76. | Not
disputed. | |
RPC 8.4(c): McBride and
Degginger lied to us about the ability of the Supreme Court to
review and modify the current practice concerning CPA awards (“The
Supreme Court has no discretion...”). Since the current
practice had been set thus by the Supreme Court, it could be changed
by the Supreme Court; an act of legislature was not required. | P.
79. | Not disputed. | |
RPC 1.1, 1.2, 1.3, 1.16:
Degginger and McBride lied about intending to withdraw from the
case, flatly refused to follow our instructions, then threatened to
withdraw when it was too late to replace Lane Powell as legal
counsel, in order to defeat our efforts to correct the errors of the
Court of Appeals and/or change the Nordstrom
precedent. 30 days is
insufficient time to locate and hire new counsel, educate the new
counsel on the case, then have the new counsel write a brief
opposing a Supreme Court petition with a cross-petition
language. | P. 84.
| Not disputed. | |
RPC 8.4(c): McBride
and Degginger lied to us about the
Supreme Court requiring briefs
to be hand-delivered to the
Court. | P. 85. | Not
disputed. | |
RPC 1.0(d): "Fraud"
or "fraudulent" denotes conduct that has a purpose to
deceive and is fraudulent under the substantive or procedural law of
the applicable jurisdiction, except that it is not necessary that
anyone has suffered damages or relied on the misrepresentation or
failure to inform. Nor is it necessary for anyone to prove damages
or reliance upon the lawyer's lies. | Not
disputed. | |
RPC
1.1, 1.2, 1.3, 1.8:
Strengthening the CPA would
have severe adverse consequences for Degginger's political friends
and supporters, and for Lane Powell's other corporate clients.
McBride and Degginger chose to act in favor of those parties rather
than as we instructed them. | P. 86. | Not
disputed. | |
RPC 8.4(c): Degginger
fraudulently billed for a second (fictional) conference call on
March 1. | P. 87. | Not
disputed. | |
RPC 1.1, 1.2, 1.3: In email
(not court documents), McBride objected to an Amicus Curiae brief
that was filed in favor of our answer to the Supreme Court petition;
that brief argued in favor of strengthening the CPA. | P.
89. | Not
disputed. | |
RPC 8.4(c): On Aug. 2, 2011, McBride lied to us about the imminence
and other particulars of the proposed partial payment from
Windermere. | P. 91. | Not disputed. | |
RPC 3.3, 4.1, 8.4(c): The Respondents lied to the Eadie court that
McBride told us of the partial payment before we told them to stop
work on the case. The Respondents also misrepresented those facts
to this Counsel. | P. 91. | Disputed. | |
RPC 8.4(c): When challenged,
Degginger stopped billing to the case and refunded some of the fees
he had charged, effectively admitting he added no value to the case
(as we claimed) and that his billings to the case had been
improper. | P. 93. | Not
disputed. | |
RPC 1.8: Degginger insisted on receiving the entire award into Lane
Powell's trust, and holding hostage to Lane Powell's fee demands, to
be paid to us when we acceded to those demands in
full. | P. 96. | Not disputed. | |
RPC 8.4(c), 3.4: Degginger lied to Michelle McNeil that he did not
know we had any problems with Lane Powell's legal
services. | P. 97. | Not disputed. | |
RPC 3.4(a), 1.16(d) : Degginger and McBride failed to maintain the
costs documentation in a form that could be claimed against
Windermere on the remand, and indicated in their comments that they
had no intention of claiming for it. When asked for the
documentation, the Degginger complained that it would be a “lot
of work” and refused to give it; representing him, Sulkin
pretended he had been asked for “legal advice” and also
refused to give it. | P. 98. | Not disputed. | |
RPC 3.3, 4.1, 8.4(c): The Respondents lied to the Eadie court about
our purpose for terminating Lane Powell's legal
representation. | P. 99. | Disputed. | |
RPC 3.3, 4.1, 8.4(c): The respondents lied to the Eadie court about
being kept in the dark during the remand. | P. 100,
128. | Not disputed. | |
McBride and Degginger had Lane Powell file against DeCourseys
despite Lane Powell's explicit promise in the fee agreement (Dec.
30, 2008), “Lane Powell will forbear for a reasonable time on
collecting the balance and will assist you your motion for attorneys
fees and costs ...” The term “reasonable time” is
defined in earlier correspondence to mean, “we will forbear on
demanding payment on the balance of the amount owed until payment on
the judgment or settlement with Windermere.” When Lane Powell
filed suit on October 5, 2011, we were still a month from “payment
on the judgment.” Forbearance was necessary because, as Lane
Powell recognized repeatedly, we are people of modest means and were
incapable of paying the invoice until payment on the judgment. In
essence, the suit was pure harassment. | P. 101,
108. | Disputed. | |
RPC 3.3: The Respondents told the Eadie court that “However,
the DeCourseys have breached and repudiated their agreement with
Lane Powell by terminating Lane Powell and interfering with payment
of Lane Powell's fees and costs.” However, Respondents failed
to tell the court of the explicit wording in the retainer agreement
that provided, “Both you and we have the right at any time to
terminate the relationship.” Respondents also failed to tell
the court that the costs and fees were awarded to DeCourseys, not to
Lane Powell, and Lane Powell had no legal claim to that money until
DeCourseys took possession of it. | P. 112. | Not disputed. | |
RPC 1.8: The Respondents' complaint (in Eadie's court) show that
Degginger and McBride were trying to: “... structure the
transaction ... at the expense of the client,” that is, to
take an early payout of the award even if it required us to take
another reduction on the judgment. | P. 113. | Not
disputed. | |
RPC 3.2, 8.1(d), 8.4 (Extortion): The day after Lane Powell filed
suit, Sulkin telephoned Paul Fogarty, who had represented us when
attempting to negotiate the invoice with Lane Powell, and threatened
that Lane Powell was willing to spend $800,000 in legal fees to
recover $300,000 from us. The purpose of the call was quite
obviously to discourage Fogarty – and any other attorney –
from representing us on contingency. And it worked. This is
“conduct that is prejudicial to the administration of
justice. | P. 110, 114. | Not disputed. | |
RPC 3.3: The Respondents misrepresented the law and precedent to
Eadie's court on the subjects of privilege and discovery. Quoting
the Tegland desk reference, they cherry-picked the wording to make
it appear it said the opposite of what it really says. And they
cite no case law because none would support their position. | P.
119. | Disputed. | |
RPC 1.6, 8.4 (Extortion):: The day Lane Powell filed suit, the
Respondents demanded that ALL attorney client confidential
information be produced in discovery, in violation of CR 26(b) and
RPC 1.6. Since intentional production of confidences in discovery
waives the privilege, this was blackmail: We must either capitulate
to the claims of the plaintiff, or have all attorney client
confidences exposed in evidence. This is also a criminal act under
State law. | P. 110, 116, 120, 126. | Disputed. | |
RPC 3.3: The Respondents argued (11/10/2011) that we had waived the
privilege, though the discovery materials were demanded before we
had spoken or written Word One to the court. They next argued
(12/5/2011) that the judge had waived our privilege, though Judge
Eadie never mentioned the word until July of the following year.
They next argued (7/9/2012) that we still held the privilege and
they could not produce privileged material to us without an ethical
violation: “Consistent with its ethical obligations, Lane
Powell has not produced documents which may be subject to
DeCourseys’ privilege claim. Lane Powell is willing to
produce those documents as long as DeCourseys agree in writing that
the privilege is waived.” Then the Respondents began
producing documents in evidence (December 12, 2012) that they
claimed were acquired under the seal of privilege. Since not all of
those statements could be true, one or more must be a
lie. | P. 124. | Not disputed. | |
RPC 4.8(c): The Respondents
lied to the Eadie Court about the total fees found reasonable by
other courts. The figures for each court are these: $356,482
(Superior) + $47,600.61 (Appeals) + $11,978 (Supreme) = $416,060.61
(total). The Superior Court added a 30% multiplier, but the
multiplier was calculated after the reasonable determination, and
was awarded to us, not to Lane Powell. | P. 151. | Not
disputed. | |
RPC 3.3: McBride lied to the
Court that “DeCourseys were very difficult clients” and
that we had proposed “outlandish” arguments, despite the
multiple times we had corrected his briefs for fact, law, grammar,
and syntactic errors, as recorded in multiple emails, and won his
contemporaneous gratitude therefor. | Not
disputed. | |
RPC 3.3, 4.1, 8.4(c): The respondents lied to the Eadie court about
many other issues, fully detailed and documented in the
chart/table/matrix entitled, “The Truth, the Lie, and the
Judge,” found in Part II, Chapter 2 of the Grievance and
included for convenience with this Reply. Lying under oath to a
judge is also a criminal act under State law. | Grievance, Part II, Chapter 2. | Not
disputed. | |
Original June 20, 2014 exhibits contained in Books 2 through 6 are
herewith resubmitted.
/signed/
Mark H. DeCoursey
/signed/
Carol DeCoursey
8209 172nd Ave NE
Redmond, WA 98052
Home: 425 885 3130
|
Next → |